Emergency Data Center Maintenance(紧急机房维护)

[复制链接]
发表于 2009-7-16 09:10:25 | 显示全部楼层 |阅读模式
时间:Saturday, July 18th 2009 - Start time: 1:00 AM PDT - End time: 2:00 AM PDT (太平洋夏令时)

SoftLayer Engineers will be replacing the upstream
back end / private aggregate switch that provides
connectivity to the rack level switch to which
your server is connected.

During this maintenance, customers will not have
access to back end / private services (DNS,
updates, update servers, NAS, iSCSI, etc). While
the maintenance window is set for 1 hour, we
expect no longer than 10 - 15 minutes of downtime.

主要影响额外服务 如dns 和备份服务等,预定1小时,预期不会超过10-15分钟。